Meyers Street Water and Sewer System Expansion

August 9, 2017
Meyers

Chazen provided design, permitting, and construction support for the installation of new water and sewer facilities for the newly formed Sanitary Sewer District No. 5, Extension No. 4 and Water District No. 6, Extension No. 3. The project included 16 parcels which were serviced by individual wells/septic systems or substandard municipal utility connections. The project involved design and construction of approximately 1,300 feet of water main and 1,200 feet of sanitary sewer main including hydrants, manholes, valves and laterals to private property. The project also required the reconstruction of the roadways affected by utility installation. This project received nearly $600,000 via a Community Development Block Grant from the NYS Office of Community Renewal.